Aggregate planning: overtime, temps or subcontracting?
When seasonal orders double, should a factory use overtime, temps or subcontracting? Across a six-month furniture model, temps beat subcontracting past 1.62 months, undercut overtime past 2.55 months and cut cost by nearly 17 per cent against hire-and-fire.