tags: ["Net present value", "Internal rate of return", "Payback period", "Capital budgeting", "Investment decisions"]
---

# NPV or IRR? Why the two can rank your projects in opposite order

## Key takeaways

- [NPV](https://khoi.co.uk/glossary#net-present-value) measures net wealth added in today's currency after covering the opportunity cost of capital, whereas [IRR](https://khoi.co.uk/glossary#internal-rate-of-return) is the discount rate setting NPV to zero (measuring return on unrecovered capital balances along the way).
- Mutually exclusive projects with different capital outlays and cash timing routinely rank in opposite order: at a 12 per cent cost of capital, a 400m VND oven earns a 26.38 per cent IRR and 120.76m VND NPV, while a 1,000m VND van fleet earns an 18.04 per cent IRR yet delivers 176.40m VND in NPV.
- The NPV lead flips at a 14.63 per cent crossover rate, matching the IRR on the incremental 600m VND outlay: below 14.63 per cent the fleet creates more wealth, and above it the smaller oven wins.
- Surveying 392 CFOs in 1999, Graham and Harvey recorded 74.9 per cent regular usage for NPV and 75.6 per cent for IRR; smaller corporate respondents scored payback (2.72 out of 4) close to NPV (2.83), without proving cash constraints caused that habit (Graham and Harvey, 2001, pp. 197–200).
- In our deterministic sensitivity test, trimming inflows across both options by roughly 8.5 per cent erases the fleet's NPV advantage; a 20 per cent shortfall leaves the fleet at −58.88m VND while the oven holds +16.61m VND.

When two mutually exclusive capex proposals rank in opposite order (one higher on IRR, the other higher on NPV), which project should an owner sign off? Corporate finance logic settles the tie by NPV discounted at your true [opportunity cost of capital](https://khoi.co.uk/glossary#opportunity-cost-of-capital), provided the firm can fund the larger outlay without straining working-capital liquidity. At a 12 per cent annual cost of capital, for instance, a 1,000 million VND delivery fleet (18.04 per cent IRR) creates 55.6 million VND more present value than a 400 million VND commercial oven line (26.38 per cent IRR).

## When to decide by NPV versus IRR, incremental IRR, MIRR and payback

Each metric inside standard [Capital budgeting techniques](https://khoi.co.uk/framework/capital-budgeting-techniques) answers a distinct financial question built around the [time value of money](https://khoi.co.uk/glossary#time-value-of-money): NPV counts absolute wealth added in currency units, IRR and MIRR express percentage rates of return, and payback tracks how long initial cash stays locked up. The decision table below assigns each tool its proper job:

| Appraisal metric | Core question answered | Best practical use case | Blind spot to watch |
|:--|:--|:--|:--|
| **NPV** (Net present value) | How much value in today's money does the project add above funding cost? | Picking between mutually exclusive options; summing value across independent projects | Sensitive to overly optimistic volume forecasts and misjudged discount rates |
| **IRR** (Internal rate of return) | What maximum cost of capital can the project bear before NPV turns negative? | Framing percentage headroom for lenders and shareholders on conventional cash flows | Favours small, front-loaded outlays; breaks into multiple roots if cash signs flip twice |
| **Incremental IRR** | What percentage yield does the extra capital between a larger and smaller option earn? | Checking whether scaling up from a smaller capex option pays off (single sign change) | Unusable when mid-life refits or lease restoration flip incremental cash signs |
| **MIRR** (Modified IRR) | What compound return emerges under explicit financing and reinvestment rates? | Resolving multiple-IRR anomalies and separating borrowing cost from reinvestment rates | Still a percentage ratio, so it still ranks smaller high-yield outlays ahead on scale |
| **Payback period** | How many years until cumulative cash inflows recover the starting outlay? | Screening maximum working-capital lock-up for SMEs facing high market uncertainty | Ignores time value of money and discards every cash receipt after break-even day |

Two textbook misunderstandings trip up capex reviews regularly: treating IRR as an annual yield on the entire starting outlay, and reading a positive NPV as instant spare cash sitting in the bank. In economic terms, IRR measures the periodic return on unrecovered capital still tied up inside the venture, and only NPV obeys value additivity (two independent projects add wealth equal to the sum of their individual NPVs).

## Worked model: why IRR picks a 400m VND oven while NPV picks a 1bn VND fleet

Opposite rankings arise whenever two mutually exclusive projects differ in upfront scale and cash-inflow timing. Take an illustrative bakery weighing two expansion quotes where floor and management capacity allow only one to proceed (assuming access to up to 1,000 million VND at a 12 per cent annual cost of capital, zero year-five scrap value, figures in millions of VND):

| Year | Oven line | Delivery fleet | Incremental stream (Fleet minus Oven) |
|:--|--:|--:|--:|
| 0 | −400 | −1,000 | −600 |
| 1 | 200 | 200 | 0 |
| 2 | 180 | 300 | 120 |
| 3 | 150 | 350 | 200 |
| 4 | 100 | 400 | 300 |
| 5 | 50 | 450 | 400 |

Discounted at the illustrative 12 per cent opportunity cost of capital, the appraisal table splits cleanly down the middle:

| Summary metric | Oven line | Delivery fleet |
|:--|--:|--:|
| NPV at 12% cost of capital (million VND) | 120.76 | 176.40 |
| IRR | 26.38% | 18.04% |
| Simple payback (years) | 2.13 | 3.38 |
| Discounted payback (years) | 2.73 | 4.31 |
| Profitability index (PV of inflows / outlay) | 1.30 | 1.18 |

Spending 400 million VND on the oven brings 200 million VND back in year one, shrinking the unrecovered balance rapidly and pushing IRR to 26.38 per cent. Once initial capital is recovered at year 2.13, however, the oven generates just 280 million VND of further undiscounted cash (680 million VND total across five years); the van fleet takes 3.38 years to break even yet collects another 700 million VND afterwards, lifting five-year receipts to 1,700 million VND.

Isolating the incremental column ("putting an extra 600 million VND to work by upgrading from the oven to the vans") leaves a single sign change and an incremental IRR of 14.63 per cent. Because 14.63 per cent clears the 12 per cent hurdle rate (where leaving that spare 600 million VND in baseline alternatives earns only 12 per cent), upgrading adds 55.65 million VND in present value, matching the gap between 176.40 million and 120.76 million VND within 0.01 million of rounding.

When I review SME equipment budgets, I apply a hard funding and liquidity filter before backing the higher-NPV option: the fleet wins only if the business can genuinely fund 1,000 million VND at 12 per cent. If hard capital rationing caps credit at 400 million VND, stretching into expensive short-term debt to chase spreadsheet NPV invites a cash squeeze; likewise, I treat payback as an outer liquidity guardrail (noting Graham and Harvey's citation of McDonald 1998 on payback approximating real-option timing under high uncertainty (Graham and Harvey, 2001, p. 200)) before ranking qualifying options by NPV.

## The 14.63% crossover rate, multiple IRRs and the reinvestment myth

The NPV ranking between the oven and the fleet flips at an exact 14.63 per cent discount rate (the *crossover rate*): below 14.63 per cent the fleet adds more net wealth, whereas above 14.63 per cent the smaller oven takes the lead.

> **Figure:** (compare) Calculated from the hypothetical cash flows in the table above. Each option's NPV is zero exactly at its own IRR (26.38 and 18.04 per cent).

```json
{
  "type": "compare",
  "columns": ["Oven line NPV", "Van fleet NPV", "Higher NPV"],
  "rows": [
    { "label": "0%", "cells": ["280.00", "700.00", "Fleet"] },
    { "label": "8%", "cells": ["166.11", "320.50", "Fleet"] },
    { "label": "12% (assumed rate)", "cells": ["120.76", "176.40", "Fleet"] },
    { "label": "14%", "cells": ["100.36", "113.07", "Fleet"] },
    { "label": "14.63% (crossover)", "cells": ["94.25", "94.25", "Tie"] },
    { "label": "16%", "cells": ["81.32", "54.76", "Oven"] },
    { "label": "18%", "cells": ["63.49", "0.98", "Oven"] },
    { "label": "20%", "cells": ["46.79", "−48.71", "Oven"] }
  ]
}
```

Because the fleet's heaviest receipts (350 to 450 million VND) arrive in years three to five, rising discount rates erode its present value much faster than the front-loaded oven.

Beyond scale differences, standard IRR decision rules break whenever project cash flows change sign more than once. Consider a short-term central kitchen lease costing −400 million VND in year 0, earning +1,020 million VND in year 1 and requiring −644 million VND for site reinstatement in year 2.

Solving zero NPV on (−400, +1,020, −644) yields two positive IRRs at 15 per cent and 40 per cent, yet at a 12 per cent cost of capital the project's actual NPV is −2.68 million VND (turning positive only inside the 15 to 40 per cent band, such as +2.78 million VND at 20 per cent) [Capital budgeting techniques](https://khoi.co.uk/framework/capital-budgeting-techniques). Whenever mid-life overhauls flip incremental cash signs, I skip incremental IRR and discount each option's NPV directly.

On the textbook reinvestment debate, neither the NPV equation nor the IRR equation forces a company to reinvest interim cash receipts at a fixed rate. Reinvestment assumptions enter only when computing year-five terminal wealth via MIRR: using an illustrative 12 per cent reinvestment rate, the oven's receipts compound to 917.75 million VND by year five (an 18.07 per cent MIRR on 400 million VND) while the fleet compounds to 2,073.22 million VND (a 15.70 per cent MIRR on 1,000 million VND), still putting the smaller oven ahead on percentage terms.

## Cash-flow sensitivity testing and the single hurdle-rate trap

A clean positive NPV offers zero protection against optimistic sales forecasts or a mispriced discount rate. In our bakery model, the fleet's 55.6 million VND edge turns out to be noticeably sensitive to realised delivery volume.

Holding upfront capex and the 12 per cent discount rate constant, deterministic sensitivity testing shows that trimming net inflows across years one to five by roughly 8.49 per cent on both options brings their NPVs dead level; at an 8.5 per cent shortfall, the oven moves ahead. Should softer demand cut inflows by 20 per cent on both projects, the oven stays positive at +16.61 million VND whereas the fleet drops to −58.88 million VND.

Read that −58.88 million VND figure accurately: it shows the vans missed the required 12 per cent return under a 20 per cent volume dip, rather than proving the firm lost all 1,000 million VND of principal or defaulted on debt; testing solvency requires overlaying bank amortisation schedules and cash reserves. Avoid applying a single company-wide hurdle rate across ventures carrying very different risks, a slip reported by over half of the CFOs in Graham and Harvey's study (Graham and Harvey, 2001, p. 232); before locking funds into illiquid assets, run downside volume cases (see [One number or several scenarios?](https://khoi.co.uk/blog/lap-kich-ban-cho-chu-doanh-nghiep)) and validate demand cheaply upfront ([checking feasibility before the plan](https://khoi.co.uk/blog/kiem-tra-kha-thi-truoc-ke-hoach)).

## What Graham and Harvey's survey of 392 CFOs reveals about real-world practice

Modern discounted-cash-flow capital budgeting traces back to Joel Dean's (1951) synthesis of earlier time-value theory by Irving Fisher (1930) and John Burr Williams (1938). On executive practice, John Graham and Campbell Harvey's (2001) study in the *Journal of Financial Economics* (polling 392 North American CFOs in February 1999 at roughly a 9 per cent response rate) confirms that finance leaders routinely pair absolute and percentage metrics (Graham and Harvey, 2001, p. 191).

Table 2 of their study records the share of CFOs always or almost always using each technique: 75.61 per cent for IRR, 74.93 per cent for NPV, 56.94 per cent for hurdle rates, 56.74 per cent for simple payback and 29.45 per cent for discounted payback (Graham and Harvey, 2001, p. 198). Scored from 0 (never) to 4 (always), smaller corporate respondents averaged 2.83 on NPV versus 3.42 among corporations topping USD 1 billion in revenue, while using simple payback (2.72) almost as heavily as NPV (2.83) and IRR (2.87) (Graham and Harvey, 2001, pp. 191, 197, 200).

Keep two methodological boundaries clear when translating those findings to owner-managed SMEs. Survey answers capture self-reported corporate policies rather than audited project disbursements, offer no direct proof that cash shortages drove payback usage, and define "small firms" within a North American CFO roster that still dwarfs a typical independent manufacturer (Graham and Harvey, 2001, pp. 196–197, 200).

## Frequently asked questions

### Should budget holders drop IRR altogether and report only NPV?

No. Both metrics belong on an investment paper. In Graham and Harvey's (2001) survey of 392 chief financial officers, 74.9 per cent reported always or almost always using NPV while 75.6 per cent used IRR (Graham and Harvey, 2001, pp. 197–198). IRR communicates the percentage margin of safety clearly to lenders and equity partners, whereas NPV should settle the final choice between mutually exclusive projects.

### How should an SME set its discount rate for equipment capex?

Base the discount rate on the opportunity cost of capital: the return available outside the project at comparable risk, rather than a bank loan's nominal interest rate alone. Graham and Harvey noted that over half of surveyed CFOs used a single company-wide rate even on overseas ventures with very different risk profiles (Graham and Harvey, 2001, p. 232). Our 12 per cent rate here serves as an illustrative baseline.

### Does an NPV of zero mean the project earns zero accounting profit?

No. An NPV of zero means project cash flows recover the initial outlay and earn the exact required return on capital, putting the discount rate right on the project's IRR. In our worked table, at an 18 per cent discount rate the delivery fleet's NPV sits at 0.98 million VND because its IRR is 18.04 per cent, while accounting profit remains solidly positive.

### When does incremental IRR fail as a cross-check on NPV?

When subtracting the smaller project from the larger one leaves a single upfront outlay followed only by non-negative differences, comparing incremental IRR against the cost of capital always matches NPV. Mid-life overhauls or end-of-lease site restoration can flip signs multiple times and yield zero or several roots, making direct NPV comparison far safer.

## References

- Graham, J.R. and Harvey, C.R. (2001) ‘The theory and practice of corporate finance: evidence from the field’, *Journal of Financial Economics*, 60(2–3), pp. 187–243. https://doi.org/10.1016/s0304-405x(01)00044-7

---

Canonical HTML version: https://khoi.co.uk/blog/npv-hay-irr-chon-du-an

> A personal blog by Le Quoc Khoi, not affiliated with, sponsored or reviewed by the University of Greenwich. “Greenwich” and “University of Greenwich” are names belonging to their respective owners. No copyrighted study materials are published here; theory and cases are retold in the author's own words and may not be fully accurate, so check the original sources.