Data & analyticsPublished Updated 7 min readRead in Vietnamese

Why project forecasts overrun: the reference-class fix

Detailed bottom-up task schedules still leave construction, fit-out and ERP rollouts systematically late and over budget. Reference-class forecasting anchors contingencies to actual historical distributions at P50 or P80 risk percentiles before contracts are signed.

View .mdLinkedIn
Ảnh bìa bài Kế hoạch dự án quá lạc quan trên Khoi Greenwich

Breaking a project into detailed bottom-up tasks still leaves most construction schemes, commercial fit-outs and ERP implementations late and over budget because of the planning fallacy. Setting defensible delivery dates and capital budgets requires switching to reference-class forecasting: anchoring schedule and cost contingencies (uplifts) to the empirical overrun distribution of comparable completed jobs at an explicit P50 or P80 risk percentile (Flyvbjerg, 2006).

How to run reference-class forecasting in three steps on a 12-project log

Reference-class forecasting turns Kahneman and Tversky's outside view into a three-step appraisal routine: select a reference pool of comparable past projects, chart their actual percentage cost or schedule overruns and add the required uplift matching the overrun probability leadership will tolerate (Flyvbjerg, 2006).

In 2004, the UK Department for Transport and HM Treasury embedded this method into Green Book rules for major public works, tying capital buffers directly to risk percentiles (Flyvbjerg, 2006):

Project reference class Required uplift at 50th percentile (P50) Required uplift at 80th percentile (P80)
Roads (172 projects) 15 per cent 32 per cent
Rail, including metro and high-speed lines (46 projects) 40 per cent 57 per cent
Bridges and tunnels (34 projects) 23 per cent 55 per cent

On the Edinburgh Tram proposal, promoters tabled a £255 million base estimate plus a 25 per cent contingency (£320 million total). Applying the DfT rail reference class independently, engineering consultancy Ove Arup added the 57 per cent P80 uplift to place realistic capital exposure at £400 million (or £357 million at P50 with a 40 per cent uplift), exposing how thin the initial reserve was (Flyvbjerg, 2006).

SME contractors pricing office fit-outs, industrial installations or custom software builds can run the exact same maths on internal handover logs. Suppose an office fit-out contractor builds a 10-week bottom-up baseline schedule under a client contract carrying 5 million VND per week in liquidated damages. Pulling completion logs across 12 comparable office jobs delivered by the same site supervisors over the past three years yields percentage schedule slippages, sorted low to high, of: 0, 5, 8, 10, 12, 15, 18, 20, 25, 30, 40, 55 (totalling 238 per cent, or a mean slip of 19.83 per cent = 1.983 weeks).

Contractual schedule commitment Historical on-time share Expected late weeks per job Expected penalty cost per contract
10-week bottom-up engineering plan 1 of 12 jobs (8.3 per cent) 1.983 weeks 9.92 million VND
11.5-week median P50 commitment (+15%) 6 of 12 jobs (50.0 per cent) 0.875 weeks 4.38 million VND
13-week P80 commitment (+30%) 10 of 12 jobs (83.3 per cent) 0.292 weeks (3.5 weeks / 12 jobs) 1.46 million VND

Committing to 13 weeks leaves only job 11 (14 weeks, 1 week late) and job 12 (15.5 weeks, 2.5 weeks late) in penalty territory, saving roughly 8.46 million VND in expected liquidated damages per contract. In competitive tendering, however, quoting 13 weeks risks losing the job to a rival promising 10 weeks. Flyvbjerg (2006) stresses combining independent review with direct financial accountability (Flyvbjerg, 2006). When pricing fixed-deadline B2B tenders, my approach is to offer a transparent two-tier bid: a conditional 10-week schedule requiring vacant site access on day one, 48-hour finish approvals and client standby charges for late sign-offs, alongside an unconditional 13-week turnkey commitment.

For a wider checklist of estimating blind spots, see the Checklist of forecasting biases, pair it with Feasibility checks before a business plan and compare how Starbucks forecasts through crisis when macro shocks break historical baselines.

What drives the planning fallacy inside delivery teams?

The planning fallacy is the systematic tendency to underestimate delivery durations and costs because estimators adopt an inside view, simulating smooth step-by-step execution while ignoring the historical base rate of everyday disruptions (Flyvbjerg, 2006; Buehler et al., 1994).

Across five experimental studies, Roger Buehler, Dale Griffin and Michael Ross (1994) pinpointed three psychological mechanisms behind this bias (Buehler et al., 1994). Estimators show pronounced actor–observer asymmetry, underestimating their own completion times while scoring others realistically. Asked when work will finish, they mentally rehearse a snag-free plan; reminded of past missed deadlines, they attribute delays to isolated external events (late joinery deliveries or last-minute client revisions), discounting their own track record.

Kahneman's Israeli curriculum case, cited by Flyvbjerg (2006), shows how hard base rates bite (Flyvbjerg, 2006). Committee members individually predicted 18 to 30 months to finish a new syllabus, even after their own domain expert admitted 40 per cent of comparable curriculum teams abandoned the task and none finished in under seven or more than ten years; the project ultimately took eight years.

Encouragingly, Studies 4 and 5 of Buehler and colleagues (1994) showed optimistic bias vanished once forecasters had to tie predictions explicitly to past completion records (Buehler et al., 1994). Before approving internal software or client delivery schedules, I require actual duration logs from the team's last five to ten comparable deliverables plus a cold estimate from a peer lead outside the project.

What 70 years of Flyvbjerg's infrastructure data reveal about strategic lowballing

Forecasting errors across major capital projects failed to shrink over seven decades because honest psychological optimism is reinforced by strategic misrepresentation—promoters deliberately trimming costs and inflating benefits to secure funding approval (Flyvbjerg, 2006).

Across Flyvbjerg's (2006) multi-country transport dataset, actual construction costs exceeded budgets by an average of 44.7 per cent in rail, 33.8 per cent in bridges and tunnels and 20.4 per cent in roads, while rail passenger traffic fell short of forecasts by 51.4 per cent on average with 84 per cent of rail schemes missing targets by over 20 per cent (Flyvbjerg, 2006). Honest technical imprecision would cluster symmetrically around zero and narrow as estimating software matured; actual error distributions remain heavily skewed with fat overrun tails across 70 years. Comparative audits cited in the paper confirm the same twin drivers across factory builds, ERP deployments and product launches.

Three governance rules to apply reference-class buffers without triggering Parkinson's Law

Bent Flyvbjerg's 2006 Project Management Journal paper (volume 37, issue 3, pages 5–15) documented the first statutory rollout of behavioural outside-view adjustments in 2004 British public procurement (Flyvbjerg, 2006). Bringing reference-class uplifts inside a private firm requires three operational guardrails.

Never import percentage uplifts from an unrelated sector: a 32 per cent highway uplift or 57 per cent rail uplift reflects civil geotechnical risk and compulsory land purchase. Software teams, retail rollouts and fit-out contractors need their own completion logs, treating P50 and P80 figures from an initial 10–15 job ledger as working anchors updated after every project close-out.

Remember also that empirical base rates fix innocent optimism while leaving political lowballing untouched whenever internal bonuses reward rosy sign-off decks and forgive final-account overruns (Flyvbjerg, 2006). Pair reference-class gates with independent quantity checks and sponsor accountability at final settlement.

Finally, guard against Parkinson's Law: broadcasting a 30 per cent time or cash reserve across task owners invites work to stretch until the cushion vanishes. In my own project governance, task crews work to tight baseline milestones while the reference-class uplift sits locked as a sponsor-level management reserve, released strictly against verified stage-gate variations.

Quick questions

How does the planning fallacy differ from optimism bias and strategic misrepresentation?

Bent Flyvbjerg (2006) separates psychological error from political calculation (Flyvbjerg, 2006). Optimism bias is an unintended cognitive illusion expecting smooth delivery; the planning fallacy applies that illusion to schedules and costs. Strategic misrepresentation happens when promoters deliberately lowball budgets and inflate demand to clear funding gates or win tenders.

How many past jobs does an SME need to build a usable reference class?

Flyvbjerg (2006) sets no rigid sample floor, asking for a pool wide enough to carry statistical weight yet narrow enough to share comparable technology, scale and site conditions (Flyvbjerg, 2006). An SME logging 10 to 15 completed contracts can still compute empirical percentiles as an opening baseline and refine them after every handover.

Does warning project managers about the planning fallacy eliminate schedule bias?

No. Citing Kahneman and Tversky, Flyvbjerg (2006) notes that naming a cognitive illusion rarely stops estimators from slipping back into an inside-view narrative once task breakdowns start (Flyvbjerg, 2006). Experiments by Buehler and colleagues (1994) showed optimistic bias disappeared only when participants were required to anchor predictions directly to past completion records (Buehler et al., 1994).

Is adding a flat 20 per cent contingency reserve safe across capital projects?

A uniform 20 per cent allowance has no empirical grounding. UK transport uplifts reported by Flyvbjerg (2006) jump from 15 per cent at P50 and 32 per cent at P80 for roads to 40 per cent and 57 per cent for rail (Flyvbjerg, 2006). Handing an unringfenced buffer straight to site crews also triggers Parkinson's Law, expanding work to consume the reserve.

References

Listed A–Z by author surname, Harvard style. A source with a DOI links to https://doi.org/…; one without links to its page or says plainly that it has no DOI.

  1. Buehler, R., Griffin, D. and Ross, M. (1994) ‘Exploring the 'planning fallacy': why people underestimate their task completion times’, Journal of Personality and Social Psychology, 67(3), pp. 366–381.doi:10.1037/0022-3514.67.3.366Cited in 1 article
  2. Flyvbjerg, B. (2006) ‘From Nobel Prize to project management: getting risks right’, Project Management Journal, 37(3), pp. 5–15.doi:10.1177/875697280603700302Cited in 1 article
Keep reading

Related articles

All articles

Was this article useful?

Rate the article from 1 to 5 stars

No ratings yet.

Comments (0)

No comments yet. Be the first.

Leave a comment

Comments are moderated before they appear. That can take a few hours.